The claim going around is that Greece just switched on its biggest ever battery, and that it's one of the biggest in Europe too. The first half of that is genuinely true. The second half is a line the companies themselves are putting out, not something anyone has independently measured.

What was actually switched on. Energy group Metlen and the Karatzis Group, a Greek industrial and agricultural firm, inaugurated a standalone battery energy storage system (BESS) near Larissa, in the Thessaly region, in mid-October 2026. The plant has 330 megawatts of power capacity and 790 megawatt-hours of storage, cost more than €170 million, and was built with a loan from the EU's Recovery and Resilience Facility. It's held through a joint venture, 49 percent Metlen and 51 percent Karatzis, with Metlen handling construction, operation and maintenance. Greek Prime Minister Kyriakos Mitsotakis and Environment and Energy Minister Stavros Papastavrou both attended the opening.

The "biggest in Greece" part checks out. Independent coverage from Energy-Storage.News and Taiyang News both describe it, in their own words, as the largest standalone battery storage plant built in Greece so far. Other Greek storage projects reported in the same coverage are considerably smaller, including a trio of batteries from developer MORE totalling 72 megawatts and 144 megawatt-hours, and a 100 megawatt, 400 megawatt-hour merchant project from ContourGlobal. At 330 megawatts and 790 megawatt-hours, the new Thessaly plant is clearly bigger than both, which is enough to support the domestic record claim.

The European claim is a different matter. At the opening, Metlen's executive chairman Evangelos Mytilineos said the company was "inaugurating the largest standalone energy storage facility in Eastern Europe" and called it "one of the largest in the European Union." No outlet covering the launch cited an independent ranking or database backing either line up, and reporting on the event itself notes the regional and EU-wide claims come from the company, not from a neutral source. They also don't match what else has been built in Europe this year: Taiyang News' own coverage of the Greek opening references a 600 megawatt, 2.4 gigawatt-hour battery under construction in Poland and a 500 megawatt project in Scotland, both bigger than the Thessaly plant on paper. Metlen's original 2025 announcement for this project was more careful on this point, describing it as "the largest standalone storage unit planned to date in Greece and one of the biggest in Europe", a softer claim than "largest in Eastern Europe" and one that at least leaves room for bigger projects elsewhere.

The bottom line: the plant is real, it's genuinely Greece's biggest standalone battery, the cost and ownership details hold up across independent reporting, and the EU funding is confirmed. But "one of the biggest in Europe", and especially "largest in Eastern Europe", are the companies' own framing rather than anything an outside party has verified, and at least two bigger European battery projects are already under construction. Call this one partly true: right on the facts that can be checked, overreaching on the superlative that can't.